The upgrade of the Monkey Mountain airstrip in Region Eight (Potaro-Siparuni) is 90 per cent complete and on schedule to finish by November 20, the Ministry of Public Works says.
Once commissioned, the airstrip is expected to accommodate larger aircraft and support night-time medical evacuations.
In a Facebook update, the ministry said work began on August 15 and the main concrete runway works are substantially complete. Crews are now finishing the runway shoulders, installing lights and painting markings to international standards.
The upgraded airstrip has a 2,500-foot by 50-foot runway made of eight-inch-thick fibre-reinforced concrete, a 50-foot by 200-foot aircraft parking apron and two 100-foot taxiways. The ministry said the lighting and markings would allow for night-time emergency flights, including medical evacuations from remote communities.
The ministry said the reinforced runway would accommodate larger aircraft, including the Dornier 228. It expects the upgrade to improve passenger and cargo services and strengthen emergency and disaster response in Monkey Mountain and surrounding communities.
The ministry’s Special Projects Unit is carrying out the work under the government’s Community Participation Model. The ministry said the project provided jobs for 60 residents of Monkey Mountain, Yurong Paru, Rukumuta and Tuseneng and gave them an opportunity to develop technical skills.