– Nandlall says government reviewing education contracts for possible legal action
The government terminated Avinash Contracting & Scrap Metal Inc.’s $1.77 billion contract to build the Karasabai Secondary School on October 30, citing delays beyond the contractual limit and the company’s failure to carry out the works in accordance with the approved programme, according to a schedule shared by Attorney General Anil Nandlall SC.
The schedule confirms that the contract had already been terminated when Kiskadee Watch visited the Region Nine site on November 17 and found two security guards there and no construction workers. In its Sunday report, Kiskadee Watch said it had been unable to reach Education Minister Sonia Parag for an update. The schedule gives no revised completion date or details of who will finish the school.
The $1,773,930,690 contract was awarded in 2022 and construction was launched in February 2023. The project missed successive deadlines, and April 2027 had been given as a revised completion date before the termination became public. In April this year, President Irfaan Ali said the contractor had been granted a three-month extension because of weather and other difficulties and warned that liquidated damages would apply if the company missed the extended deadline. The schedule does not say whether any damages were imposed or recovered.
The 10-building complex is designed to accommodate 500 students in classrooms and 250 in dormitories. It is intended to serve Karasabai and surrounding villages, including Tiger Pond, Cracrana, Tsushima, Kokshebai and Yurong Paru. The Vigilant Political Action Committee had called for a review of the contractor’s performance and asked whether damages had been imposed. It also cited reports that some children were still being taught under a tree and a benab.
Questions would now likely be raised as to whether debarment procedures would be put in place in relation to future bids by Avinash Contracting.
Government reviewing possible claims
Speaking on Issues in the News on Tuesday, Nandlall said the Ministry of Education had asked the Ministry of Legal Affairs’ Contract Review Unit to examine contracts for schools and other education facilities. He said he would release a schedule identifying the contractors, termination dates and reasons so the public could see what action the government was taking when it found breaches.
“Legal proceedings will be filed if that is the advice of members of our review team,” Nandlall said. He said the government could seek compensation for breach of contract, recovery of losses and liquidated damages where the contracts provide for them. He did not identify any claim already filed in connection with the contracts on the schedule.
The government has previously sued over unfinished education projects. Stabroek News reported in 2021 that Nandlall filed claims against BK International and Courtney Benn Contracting Services and their insurers over the Yarrowkabra Secondary School and St Rose’s High School projects, respectively. The State also filed a separate claim over the Linden Technical Institute dormitories. In August, Kiskadee Watch reported that Nandlall had raised the prospect of legal action over the long-delayed Port Kaituma stelling, depending on the findings of a contract review.
Two projects listed at six per cent complete
The schedule lists 14 entries, three of which give neither a termination date nor a reason. Among the dated entries is the $310 million students’ dormitory at Jawalla, Region Seven, awarded to Sheriff Construction Inc. Work began in December 2024 and was originally due to finish in October 2025. The contractor sought an extension to February 2026, but the schedule put progress at about six per cent. It recorded a $46 million mobilisation advance and a $7 million interim payment certificate, from which $3.6 million was deducted. The termination letter is dated November 5.
Two contracts at Kopinang, Region Eight, also had termination letters dated November 5. The schedule says Urban Edge Builders Inc. received an $84 million mobilisation advance on its $280 million dormitory contract, with no further payments recorded. The company sought a 12-month extension, citing an additional requirement to construct a school building. The schedule says the termination was issued subject to a review of the contractual obligations, the justification for the extension and the status of the bonds and advance.
Blue Print Builders Inc. received a $52 million advance on its $149 million contract for a multipurpose hall and kitchen at Kopinang. The schedule says only six per cent of the work had been completed after about seven and a half months and cites unsatisfactory progress.
At Vreed-en-Hoop, a $279.8 million contract awarded to D&S Construction for two blocks of the secondary school was listed with an October 27 termination letter. The schedule put progress at 49 per cent on October 15, against a target of 91.2 per cent, and cited poor progress and inadequate resources.
Other entries in the schedule
| Project | Contractor | Termination letter | Grounds cited in the schedule |
| Monkey Mountain students’ dormitory, multipurpose hall and kitchen, Lots 1 and 2 | K’s Trucking and Construction | June 29, both lots | Failure to carry out the works, inadequate financial, technical and staffing capacity, and failure to correct defaults |
| Kwakwani Secondary female dormitory, Lot 1, and rehabilitation of the male dormitory and kitchen, Lot 2 | Rahaman Construction and Transportation Services | March 10, both lots | Failure to start and carry out the works, inadequate mobilisation and persistent non-compliance |
| Reconstruction of Kwakwani Secondary School | Modular Construction Services | July 8 | Failure to start and carry out the works |
| Extension of Dora Secondary, Lot 2 | 4S Security & Building Enterprise | March 10 | Inadequate mobilisation, failure to respond to correspondence and failure to take corrective action |
| Stewartville Secondary staffroom extension | I.S. Contracting Services | — | — |
| Construction and furnishing of home economics and industrial technology labs at St Cuthbert’s | Jemcorp Engineering & Imports | — | — |
| Rehabilitation of Wiruni Nursery | Rawl Davis Contracting Services | — | — |
Kiskadee Watch reported earlier this month that Parag had warned contractors of penalties for unjustified delays. She said some education contracts had already been terminated and that the ministry was monitoring work that had resumed under replacement contractors. She also said consultants responsible for overseeing the works would be held accountable.