Just days after the two-day blackout triggered by problems at the Canefield substation, GPL’s No. 53 Village, Corentyne substation also went down yesterday leaving customers without power for around 9 hours.
In a video statement, senior Guyana Power and Light (GPL) official, Kesh Nandlall said that at around 1.30 am yesterday, the feeder at the No. 53 substation tripped and fed back into the substation causing damage to the busbar. Around 5,000 customers from No. 53 Village towards Williamsburg were affected.
Around 10 last night GPL said that all affected customers from No.53 Village to Williamsburg had been repowered.
“The remedial works at the #53 Substation have been completed, and electricity supply has been restored to all customers affected by the earlier system disturbance”, the company said. GPL apologized for the outage.
Discussion