The two-day blackout in East Berbice/Corentyne from Thursday night to last night adds to the long list of management aberrations that the government and its public agencies have to address. The starkest one at the moment is the ongoing Commission of Inquiry into the sinking of the MV Barima with the loss of 100 lives. That incident is yet to produce a single act of public accountability by those in charge which was only made worse by the instituting of murder charges against two crew members and an employee of the Transport and Harbours Department.
In a statement last night, President Ali said: “The immediate priority must be restoring electricity. But this matter will not end with the restoration of supply. There will be a full and thorough review of the circumstances that led to this failure, the adequacy and effectiveness of GPL’s response, and the measures necessary to prevent a recurrence”. That sounds suspiciously as if nothing will happen.
There is a great likelihood that the two-day outage will be just a blip on the PPP’s radar. It occurred in one of the major constituencies of the ruling party and so there is usually a greater keenness to forgive and forget.
Yet, there are serious matters that must be addressed. Thousands of persons have lost food, business and incurred additional costs as a result of the two-day outage. They deserve to be compensated and credited with two days of free electricity.
What exactly transpired at the Canefield Substation on Thursday? Why could it not be contained and why is GPL continuing to experience these major incidents despite the billions of dollars being expended in upgrading contracts? Are contractors being held liable for these failures?
As has been asked before by Kiskadee Watch what has the advent of the richly paid Dominican Republic consulting firm InterEnergy brought to the table in terms of stabilizing the power system and reducing major incidents such as the one on Thursday? Nothing has changed and this contract, controversial from the very start, should be reviewed.
It will be evident to the President, his ministers and advisers that a two-day shutdown in a populous part of the country is an immediate disincentive to prospective investors particularly those who are to be attracted to the second gas-to-energy project and its multiplier effects.
What happened on Thursday in Berbice has underlined how GPL has lurched from one crisis to another without clear guidance on what its problems are and how they can be remedied. Instead, various solutions have been grafted on top of each other creating incompatibilities. Overloading of networks, poor maintenance and defective parts also feature regularly.
The regulatory body, the Public Utilities Commission, which should be holding frequent hearings on GPL and taking a keen interest in its activities in light of the looming gas-to-energy project, will be heard from on this matter in around a year after which it will declare that no penalties will be applied against GPL and the wretched cycle of breakdowns and incompetence will continue.
The Private Sector Commission which is usually at the beck and call of the government has so far not issued a statement on this matter. It continues to expose its self-interest and political leaning in deciding which matters require urgent attention. Does the Guyana Manufacturing and Services Association have any idea of the impact of the two-day outage on manufacturers in East Berbice-Corentyne?
The power company has been the source of much grief for the people of this country in the last five decades. It is frightening that it is expected to soon intersect with another source of worry – the approximately US$2b 300 MW gas-to-energy operation. It is expected that the public will experience great trepidation as the end of the year approaches.
Discussion