Palmyra cultural markets delayed over land issues – Auditor General’s report

President Irfaan Ali (centre) on the day he had made the announcement of the cultural market.

Two  Cultural Markets at Palmyra, Corentyne – the brainchild of President Irfaan Ali – have been delayed over land issues according to the 2025 Auditor General’s report which was recently tabled in Parliament.

The disclosure underlines the haphazard manner in which government projects are being launched. In this case land matters had not been resolved at the point that the contracts had been awarded.

The Auditor General’s report said that an award for the construction of the One Guyana Cultural Market, Lot 2, at Palmyra was made on December 24, 2025 by the National Procurement and Tender Administration Board (NPTAB) to the lowest responsive bidder in the sum of $408m. The contract was signed on December 24, 2025 with a duration of 12 months and a commencement date of January 28, 2026 with a planned completion date of January 28, 2027.

However, the Auditor General’s report said that at the time of reporting in September of 2026, the commencement date was revised to July 14 2026 with a new completion date of July 14, 2027. 

The contractor received a mobilization advance of $72m or 15% of the contract sum. Physical verification was carried out on July 23, 2026 and only site clearing work had begun. 

However, the Audit Office was advised by the Ministry of Local Government that the start of work was delayed “because of land ownership matters with the proposed site”.

The Head of the budget agency told the audit office that the project suffered a six-month delay because of the land ownership issue and review of the design to be accommodated on the available land.

In its recommendation, the Audit Office admonished the Head of the Budget Agency to ensure that due process is followed for all planned development works and that all the pertinent approvals are in accordance with the contract.

The exact problem occurred with the award for the construction of another One Guyana Cultural Market at Lot 3 at Palmyra. A contract for $334m was signed also on December 24, 2025 with a duration of 12 months and a commencement date of January 28, 2026 and projected completion on January 28, 2027.

At the time of reporting in September 2026, the start date was revised to July 14, 2026 with a new completion date of July 14, 2027. The contract received a mobilization advance of $50m. Physical verification carried out on July 23, 2026 showed that only site clearing works had started. The Audit Office was told that work had been delayed because of “land ownership matters”. The Audit Office again recommended that due process be followed. 

President  Ali had announced on August 1st 2024 that a national cultural market would be established in Palmyra, Region Six, to serve as an educational and talent-showcasing hub inclusive of a safe space for families.

The Department of Public Information (DPI) reported that Ali unveiled this initiative  when he joined Guyanese of African descent to celebrate the 186th Emancipation Anniversary.

Ali, DPI said, explained that plans are in place to promptly develop and complete the hub to showcase upcoming festivals. “As we build the new stadium, and as we build facilities around the stadium, and as we build hotels, an important part of why people will come to Region Six is to be part of this national cultural market.” The market, according to the DPI, is envisioned to encapsulate all facets of the country’s culture, including food, clothing, dance, music, and art. Additionally, the historical context of emancipation and the abolition of slavery is a pivotal part of the initiative. “This will be a symbol of the importance of culture in bridging gaps and bringing people together.  The importance of culture in economic and social revolution. The importance of culture in developing healthy lifestyle… [and] the importance of culture in celebrating the unity of our people and our country,” Ali underscored.

DPI said that Senior Minister in the Office of the President with responsibility for Finance and Public Service, Dr Ashni Singh, along with technical personnel were tasked with conducting consultations with culture groups to advance the plan and within six weeks, community consultations would  begin to formalize plans and establish a committee.

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter