Shoddy work, costly consequences

Late last week, Region One Chairman Brentnol Ashley was forced to order an immediate halt to the construction of an extension of the Arakaka Health Centre in the Barima-Waini region after discovering what was described as substandard construction practices. According to a press release issued by Region One, it was found that tail-end sand and mud were being used in the casting of foundations and columns. A photo accompanying the release revealed cracks along a slab that might have been the foundation.

It is well known that core foundation materials for buildings in Guyana are concrete, made of cement mixed to specific requirements with steel for reinforcement. Even this depends on the size and usage of the building as pile driving is sometimes necessary. The greenest contractor must be aware that the integrity of a building depends heavily on what goes into its foundations and structural components. If these are compromised, the consequences could be quite serious. Therefore, what came to light in Arakaka last week was not merely a matter of poor work. In fact, it ought to be viewed as criminal, since a health centre would likely be a high-traffic building. Moreover, the halt in construction means that the residents who need the health centre will now have to wait much longer for its completion.

Just over two years ago, President Irfaan Ali had summoned contractors from all around the country to a 5:30 am meeting at State House. There, he had proceeded to lambaste them, along with the government officers responsible for overseeing their contracts, over delays, failure to start projects and a plethora of other shortcomings. The performative nature of that event was roundly criticised by political and social commentators. They were right. Nothing much appears to have changed.

The complaints are myriad, and they are not confined to missed deadlines or contractors who seem unable to get their act together. Increasingly, there are reports of defective workmanship, the use of inferior materials and projects that fall short of the standards expected of infrastructure intended to serve the public for many years.

In March, the Ministry of Housing terminated the services of a contractor responsible for infrastructure work in sections of the Stewartville Housing Area after repeated engagements and reminders about contractual obligations failed to produce the required improvement. Approximately 100 of the nearly 1,000 allocated house lots were affected by delays in work that included roads, culverts, bridges and water distribution networks. The outstanding work had to be put out to tender again, adding another layer of frustration for people who had already been allocated land and were anxious to begin building their homes.

That was by no means an isolated example. Contractors have been dismissed from other projects, including the Young Professionals’ Homes programme, following concerns about construction standards. Contracts for a packaging facility and a fishermen’s wharf were also cancelled after auditors identified defective materials, poor workmanship and incomplete structures. Furthermore, last year, complaints about concrete suppliers prompted warnings from the Ministry of Public Works, with independent testing reportedly revealing that some supplies fell significantly below the required strength specifications.

Taken together, these incidents raise more questions about the systems governing construction in Guyana, particularly the execution of publicly funded projects. Some, including the Bamia School and the Belle Vue Pump Station pointed to contractors not being evaluated before they were awarded multimillion-dollar contracts. So if there are mechanisms in place to ensure that materials meet specifications and that work is properly supervised, perhaps they are not being observed. It does appear that problems are often discovered only after a project has fallen behind schedule or someone has raised an alarm. Incredible, considering that public projects usually have a paid consultant overseeing them.

Guyana also has a Public Procurement Commission, which says that its mission is “To promote transparency, competition, equity, the achievement of value for money, sustainability and environmental best practices in the Public Procurement System.” The Procurement (Suspension and Debarment) Regulations 2019 provide for exclusion from public procurement for periods ranging from one to ten years. It would appear that what currently exists is not being used effectively or might not be sufficiently robust to address the problems being encountered.

Attorney General Anil Nandlall had indicated in April that the government intended to review and modernise the Public Procurement Act, as well as the standard bidding documents and contracts. This would be a good opportunity to address obvious longstanding weaknesses in the procurement system. Was this review done? And if not, why not?  

Equally important is the need for independent materials testing and regular inspections at critical stages of construction. This should not be left entirely to contractors, consultants or the agencies commissioning the work. There should be random, unannounced inspections, independent laboratory testing where appropriate, and a requirement that payments be linked to verified progress and compliance with specifications.

Ultimately, the government needs to recognise that the billions being spent on infrastructure are not an end in themselves. Roads, bridges, schools, hospitals, housing schemes and other public facilities are supposed to improve people’s lives and provide lasting value. A health centre built with compromised materials, a road that deteriorates prematurely, or a long delay in completing a school represents more than contractual failure. It points to dereliction in protecting public investment and the people who depend on it.

It is not enough to put on a public show about getting tough with contractors. It actually needs to be done. Citizens do not need to see President Ali or any other member of the government flexing their muscles on this, because admonitions and expressions of dissatisfaction, however forceful, cannot substitute for an effective system of accountability. If there is less public theatre and more institutional discipline, the results will be visible.

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter