PARAMARIBO, (Reuters) – Malaysian state-controlled energy producer Petronas still expects first gas from its offshore Block 52 project in Suriname in 2030 and is targeting startup in the first half of that year, CEO Tengku Muhammad Taufik said yesterday.
Taufik said the Block 52 gas development, known as KrakaWi, contains nearly 4 trillion cubic feet of gas resources, including an estimated 2 trillion cubic feet of reserves.
Drilling is underway at two prospects in Block 66 to test potential resources of about 1 billion barrels of oil equivalent, Taufik added.
Taufik said Block 52 has already unlocked more than 1 billion boe of recoverable resources, while early work at Block 66 indicates the potential for a similar volume.
Petronas and Suriname state oil company Staatsolie said in a separate statement they had taken a final investment decision on the Sloanea gas field, the country’s first offshore gas development, but did not disclose the project’s cost.
Suriname President Jennifer Geerlings-Simons said the project would require about US$1.6 billion in investment.
Staatsolie CEO Annand Jagesar said the company’s 20% stake in the project would require about $320 million in funding, which would be financed through an existing loan facility.
The development will include gas production wells, subsea infrastructure and a floating liquefied natural gas facility, which Petronas said would be the first such development in the Guyana-Suriname basin.
Staatsolie has also said the project could yield offshore oil for export if crude is found to be commercially viable.
Following neighbouring Guyana’s emergence as a major oil producer with output exceeding 900,000 barrels per day, Suriname is also betting on offshore developments led by international energy companies to produce and export crude and gas.