The East Bank corridor road project is 70 per cent complete and is expected to be finished by March 2027, although the Government is hoping to substantially complete the works before the end of this year, Public Works Minister Juan Edghill has disclosed, while confirming that changes to the engineering design and additional road widening have pushed up the project’s cost.
Edghill made the disclosures in the National Assembly last Monday, where Opposition MPs Saiku Andrews and Ganesh Mahipaul, among others, questioned the project’s progress, revised cost and the Government’s initial planning.
The Assembly had resolved itself into the Committee of Supply to consider requests for supplementary financing.
The minister said the project, which runs from Good Success to the Timehri Police Station, had been divided into three sections, with varying levels of progress. Providing a breakdown, Edghill said Section A, from Good Success to Supply, covers 8.72 kilometres and is 68.68 per cent complete. Section B, from Supply to Soesdyke, spans 9.55 kilometres and is 81.46 per cent complete, while Section C, from Soesdyke to the Timehri Police Station, covers 5.24 kilometres and is only 1.8 per cent complete.
Commuters have complained bitterly over the years about the dislocation and delays caused by this project on the main route to the airport.
The minister acknowledged that the ongoing construction continues to affect commuters, but said traffic management had improved significantly. He also said the Government was seeking to accelerate execution, noting that the construction delays and traffic congestion affected people’s daily routines and travelling time.
Andrews questioned why the project had gone over budget and whether the additional expenditure would require further borrowing. Edghill confirmed that the project had been revised, explaining that two major changes had contributed to the increased cost. He said the original engineering design catered for approximately 10.7 tonnes per axle, but this was increased to 15 tonnes per axle to accommodate the heavier vehicles now using the corridor.
The second adjustment involved widening sections of the roadway as much as possible, from drain to drain, without acquiring private properties. Edghill said these changes were necessary because of the significant increase in traffic associated with Guyana’s development and expanding infrastructure network. “When this road was designed with support of the technical people from the IDB (Inter-American Development Bank), taking into consideration the traffic count and usage, the road was designed at 10.7 per axle,” he explained.
However, he said traffic along the corridor had multiplied five to six times since the original design was prepared. He added that the Government had subsequently decided that roads would be constructed to accommodate 15 tonnes per axle, with axle-load testing now being conducted at several locations across the country, including the Linden-Mabura Road, quarries and along the East Bank corridor.
Andrews questioned the Government’s initial planning, arguing that the revised specifications and additional expenditure had implications for the country’s finances. He asked how the Ministry, with the technical information available to it when the project was designed, had failed to anticipate the heavier axle loads and account for them in the original budget.
In response, Edghill said the decision to increase the axle-load capacity was based on changing traffic conditions and the need to ensure the road could withstand the demands being placed on it. He also confirmed that the additional expenditure would be financed from the Consolidated Fund rather than through another loan or an amendment to the existing loan agreement.
The approximately 23.7-kilometre East Bank Demerara Road Improvement Project, which runs from Good Success to Timehri, was awarded to China Road and Bridge Corporation (CRBC) for US$75.89 million in February 2024. It is being undertaken with funding support from the IDB.
The project includes upgrading the roadway, reconstructing bridges and culverts, constructing concrete drains, and installing sidewalks, cycle lanes, streetlights and traffic signs. The works are also intended to improve connectivity between the East Bank corridor, the Cheddi Jagan International Airport, Timehri and the Soesdyke-Linden Highway.