Exxon replaces section of Gas-to-Energy pipeline after `anomaly’

Alistair Routledge

ExxonMobil has replaced a section of the Gas-to-Energy pipeline after detecting an “anomaly” earlier this year and is sending material removed from the line to laboratories in the United States to determine what caused it.

ExxonMobil Guyana President Alistair Routledge told a press conference yesterday that the company initially inspected the affected section and fitted a clamp. Crews returned in recent weeks with additional equipment and replacement pipe, removed the section and carried out further inspections.

“The line is still full of nitrogen and inert. It’s in a safe state,” Routledge said. He said the company was sending the removed material to US laboratories and would use the results alongside data gathered during the inspections.

Routledge did not say what had caused the anomaly or whether the section had leaked. He said the company wanted the line ready when the gas plant could receive gas and was assessing its long-term integrity.

“We want to make sure that for the life of the operation of Gas-to-Energy, that this pipeline has its integrity,” he said.

A November 5 Maritime Administration Department notice retained December 1 as the scheduled end of the offshore inspection and maintenance programme. ExxonMobil had announced in October that work would address a finding on a nearshore section of the line off Crane, West Coast Demerara.

Opposition Leader Azruddin Mohamed had alleged that the pipeline had ruptured, citing bubbling at the water’s surface. The Environmental Protection Agency and the Maritime Administration Department rejected that allegation but acknowledged an anomaly and said further inspections were being carried out.

Stabroek News reported last November that the pipeline had been completed in December 2024 and was being kept in a preserved state while work continued on the facilities at Wales. The line is intended to carry offshore gas to a 300-megawatt power plant and a natural gas liquids facility. It has sat unused for nearly two years.

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter