Exxon weighs up to four Stabroek wells ahead of prospecting licence expiry

ExxonMobil is considering drilling three or four exploration and appraisal wells in the Stabroek Block in the first nine months of 2027, ahead of the October expiry of the prospecting licence for the acreage it can access, ExxonMobil Guyana President Alistair Routledge said yesterday.

“We think maybe three or four exploration wells in the first nine months of next year may be possible,” Routledge told a press conference. He said some could be appraisal wells, depending on the results of drilling already underway.

A sixth rig, a semi-submersible, joined ExxonMobil’s fleet over the weekend and is working on the White Tip well southeast of the Hammerhead development. Routledge said the company’s five deepwater drillships were working mainly on wells for upcoming developments, with some also assigned to exploration and appraisal.

He said the company had used artificial intelligence to review seismic data for prospects it might have missed. Among the areas it is examining is the vicinity of Ranger, where the Rockhead well encountered oil-bearing sandstone earlier this year. Routledge said similar formations identified in the seismic data were close enough to Ranger to be considered for a possible joint development if further drilling confirmed their potential.

“There’s always uncertainty until you run the drill bit into the rocks,” he said.

Stabroek News reported in January that part of the Stabroek Block was under force majeure because it lies in waters disputed by Venezuela. Routledge’s October 2027 timeline referred to acreage available for exploration.

In a separate update on projects already under development, Routledge said changes identified through work on Haimara could save as much as US$200 million on Longtail. Construction of Longtail’s vessel hull began in China several months ago, he said, while Whiptail and Hammerhead remain on schedule and are running at or slightly below budget.

Guyana approved the US$12.5 billion Longtail project on November 12. It is the country’s first offshore development to target natural gas found independently of crude oil, and ExxonMobil expects production to begin in 2030. Whiptail and Hammerhead are expected to start up in 2027 and 2029, respectively.

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter