$700m water treatment plant opens on Leguan

The treatment plant

A new water treatment plant was commissioned on Leguan yesterday, bringing treated water into service on the Essequibo River island. 

The facility can treat two million litres a day and is intended to serve about 2,807 residents across 701 households. The community of Success, however,  still needs a new transmission line to connect to the plant.

President  Irfaan Ali said residents of Success raised the need for a new line when he visited Leguan the previous week. He said he discussed the matter with Guyana Water Incorporated (GWI) Chief Executive Officer Shaik Baksh the night before the commissioning.

“So in the next month we hope that that transmission will be completed so that Success will be connected to the water treatment plant,” Ali said. He said the connection would extend treated water service to every household on the island.

Earlier in the ceremony, Baksh said GWI expected to begin laying new eight-inch transmission lines by January, with the works reaching Success and Uniform. He said the lines would improve water pressure and extend the reach of the treated supply. Ali’s target would put the Success connection in late December. The remarks left open whether the connection would be carried out separately from the wider pipeline works.

Baksh said GWI measured water pressure during visits to several communities, including Success, Henrietta, Uniform and Canefield, and found good pressure in most of the areas checked. Further transmission and distribution works are planned to improve flow, pressure and reliability across the island.

Baksh also announced plans for a refill station at the treatment plant after residents told him they were paying $700 for a five-gallon bottle of water. He said GWI plans to offer the same quantity for $100 and would begin preparing the site shortly. He gave no opening date.

Leguan Neighbourhood Democratic Council Chairman Jainarine Singh said treated tap water could reduce what families spend on bottled water and on cleaning products they use to remove reddish stains. He urged residents to conserve water and address leaks.

Region Three Chairman Inshan Ayube said the island already had round-the-clock water service before the commissioning. He recalled a time when residents pooled money to buy fuel to run the water supply.

GWI’s project brief listed the plant’s construction cost at approximately $700 million. Public Utilities and Aviation Minister Deodat Indar put the cost of the plant itself at $687 million during the commissioning. With the new production well and planned work on the transmission and distribution network, total investment in Leguan’s water supply is expected to reach about $1.2 billion.

A part of the treatment plant

The plant draws raw water from the new well. Dr. Taamjeed Rahmaan, representing the joint venture between Sigma Engineers Ltd. and Hebei Wansheng Environmental Protection Engineering, said the facility uses multiple stages of filtration, including activated carbon, and automatically monitors key water quality measures in real time. Baksh said the treated water had an iron concentration of 0.05 milligrams per litre.

Leguan is the first of five new plants to enter service under the Water Supply Improvement Project. GWI is executing the project with loan financing from the Caribbean Development Bank and the European Investment Bank. The wider project includes six new wells and approximately 70 kilometres of transmission pipelines across Regions Two, Three, Five and Six.

The other plants are at Wakenaam, Maria’s Delight, Bath and Adventure. Indar said he expected the Wakenaam plant to be completed in early January and the Bath and Adventure facilities in March 2027.

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter