Gas-to-energy project further pushed back to March


–Jagdeo puts combined-cycle stage around June; no new date for promised 50% cut in electricity bills

Vice-President Bharrat Jagdeo on Thursday confirmed that the single-cycle stage of the long-delayed Wales Gas-to-Energy project is now expected by the end of March 2027. 

The government had most recently assured that the first turbine would supply about 57 megawatts to the national grid by the end of this year.

Estimated now at a total cost of more than US$2b this 300 MW project had been promised from as long ago as 2023 and is still to produce a single watt. It has been mired in a series of problems and critics say that the management of the project has underlined the PPP/C government’s incapacity and poor planning. The unavailability of the power has also meant that Guyana has incurred enormous costs to hire generators and 20MW of additional power is due before the end of the year.

A photo of one of the gas to energy sites in September this year. (Office of the Prime Minister photo)

“The new timeline we have for the single cycle unit is the end of the first quarter of next year,” Jagdeo told the Guyana Manufacturing and Services Association’s awards dinner. He put completion of the combined-cycle stage at “June or so”.

Jagdeo acknowledged that the project had been significantly delayed and costs had risen. Discussing a dispute with the contractor, he said one claim concerned whether an access road for which ExxonMobil was responsible during preparatory works had been ready on time and met the required standard. He said the government disputed the claim.

Another major dispute had centred on the costly works that were needed to stabilize the soil at the Wales site. Critics charged that no adequate geotechnical investigation of the soil had been done.

Jagdeo’s remarks put the March timetable given by Prime Minister Mark Phillips on Monday in Parliament in context. Responding to APNU MP Vinceroy Jordan in the Committee of Supply, Phillips said four turbines would be running by the end of the first quarter of 2027. He gave no separate update on the first turbine, which his office had said in September would supply power to the grid by year-end.

Guyanese still waiting on promised 50% cut

And nearly a year after President Irfaan Ali’s deadline for a 50 per cent cut in electricity bills passed, Guyanese are still waiting for the reduction. Phillips reaffirmed the pledge on Monday and gave no date for the tariff cut.

Ali told the National Assembly on October 10, 2024 that electricity bills would be cut by 50 per cent before the end of 2025, as reported by Stabroek News. In November 2024, he said the reduction would take effect even before the project was completed. By January this year, Ali told the newspaper that the pledge stood but gave no new date for consumers to see the reduction.

As opposition MPs peppered him with questions on Monday about the additional $24.688 billion sought for the project, Phillips returned to the pledge. “We made a commitment to the people of Guyana that they will get 300 additional megawatts of power at 50% of what they are paying for now,” he said.

“Yes, there is a delay,” Phillips said. “So what do you do?”, he asked. When opposition members objected, he repeatedly told them to “hold on” and said the government had to decide how to keep construction going. The earlier allocation had been used, he said, and the government opted to seek more money to finish the project and avoid litigation.

APNU MP Terrence Campbell asked whether the government had placed its order with Siemens Energy for the Phase Two turbines without making a down payment. “We’ve already paid 10 per cent,” Phillips replied. He said the $4.25 billion in the latest request would cover a second 10 per cent payment. When Campbell asked where the money for the first payment had come from, Phillips said it was drawn from the previous supplementary provision.

Campbell also asked for an itemised breakdown of the $12.1 billion earmarked for Lindsayca’s work on the Phase One power plant and natural gas liquids facility. Phillips said the money had yet to be paid. Pressed on whether he had the breakdown, he replied, “We have it,” and said he would provide it to Campbell. He did not read out the figures.

APNU MP Sharma Solomon asked whether materials bought in advance had incurred storage, brokerage or insurance costs while the project was delayed. Phillips said there was no procurement and storage activity of the kind Solomon described associated with the supplementary provision.

Shipping waiver and audit

APNU MP Sherod Duncan, citing financing documents tabled in the House, asked whether reimbursements were affected in the period between the earlier deadline for drawing on the US Export-Import Bank loan and the request for an extension. He also asked whether the revised December 30, 2027 deadline he cited would affect fees or the timetable for the works.

Phillips said a shipment had been delayed while a waiver for a barge was being sought. “We got the waiver and everything is back on stream now,” he said, adding that the delay had resulted in no additional expenditure. He did not address whether reimbursements had been affected during the period Duncan identified.

Jordan asked whether an independent technical or financial audit had been conducted on the power plant, natural gas liquids facility, pipeline or associated contracts. Phillips said the project would be audited. When Jordan sought to explain why he had asked, the chair asked whether he had another question and then put the provision to a vote. The committee approved it.

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter