Linden–Mabura road contractor faces penalties if December 8 deadline is missed – Edghill

Part of the Linden to Mabura Road (Ministry of Public Works photo)


– Committee approves $4.769b to extend road by 30 kilometres towards Kurupukari

The contractor upgrading the 121-kilometre Linden–Mabura Hill road faces financial penalties if it misses a revised December 8 completion deadline, Minister of Public Works Juan Edghill told the Committee of Supply on Monday.

During the consideration of a request for supplementary funding, Edghill said the original stretch was 89 per cent complete and that the December deadline followed an extension requested by the contractor. “If they go past the 8th of December, clauses of the contract will be invoked which will include liquidated damages,” he said. The project has faced severe delays.

The minister gave the update as the committee considered and approved $4.769 billion in supplementary funding to extend the road a further 30 kilometres beyond Mabura Hill towards Kurupukari. The sum formed part of $27.4 billion in additional funding approved for the Ministry of Public Works.

A Partnership for National Unity (APNU) MP Saiku Andrews said the project was over budget and asked Edghill to explain why the additional spending was listed as an accelerated work programme. We Invest in Nationhood (WIN) MP Dr Ryan Richards asked what had prompted the request for additional funds and whether the completion date had changed.

Edghill said the supplementary funds would come from the Consolidated Fund and pay for the work beyond Mabura Hill. “We’ve been able to engage the contractor at the same 2021 rate to push another 30 kilometres,” he said. Andrews welcomed the use of the original bid rate for the additional work and pressed the minister for the completion date of the first stretch.

APNU MP Dr Terrence Campbell asked whether the allocation covered construction of the Kurupukari Bridge, since the bridge was named in the  line item. He also asked when work on the bridge would begin. Edghill said the name identified the endpoint of the road corridor and that the supplementary allocation covered road works. He gave no start date for the bridge.

WIN MP Nandranie Persaud pointed to Finance Minister Dr Ashni Singh’s 2026 budget speech, which included Kurupukari among several bridge projects covered by a combined $12.2 billion provision. The speech gave no figure for the Kurupukari Bridge alone. It separately provided $10.4 billion to complete the Linden–Mabura Hill road and $7.6 billion to begin work on the Mabura Hill–Kurupukari road.

Stabroek News reported in January this year that the original Linden–Mabura Hill upgrade was 62 per cent complete. Edghill had warned the Brazilian contractor, now known as Alya Construtora, in April 2025 when only 40 per cent of the work had been completed despite 80 per cent of the original contract period having elapsed.

The sod was turned in May 2022 for the US$190 million project, which was financed by the Caribbean Development Bank, the United Kingdom and the Government of Guyana. The road forms part of the Georgetown–Lethem corridor and is intended to improve access to hinterland communities and strengthen trade links with Brazil.

The initial completion date for the project was June 19, 2025. That was then shifted to October that year. A year later the project is still to be completed.

In February, 2025, Edghill had said that the contractor responsible for the project had proposed several changes, including invoking price escalation clauses. These proposals were taken before the Dispute Adjudication Board, with ongoing negotiations and dialogue with the contractor. 

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter