It is beyond a doubt that all our knowledge begins with experience.
German philosopher Immanuel Kant
Last Monday, the National Assembly approved two Supplementary Estimates totalling $89.8 billion of which $24.7 billion relates the Gas-to-Power Project. In today’s article, we discuss the escalating cost of the Project which began in 2022 at an estimated cost of $104 billion and an expected completion date of December 2025. One year on, the Project remains incomplete, with a revised completion date of December 2027 and a four-fold increase in cost. This does not include the cost of US$1 billion, equivalent to G$208.5 billion, associated with the acquisition and laying of the pipeline to bring the gas from ExxonMobil’s offshore operations to Wales, West Bank Demerara, where the plant to convert the gas to electricity is being constructed.
Historical background
The 2016 Petroleum Sharing Agreement between ExxonMobil’s subsidiaries and the Government of Guyana provides for the extraction of fossil fuels in Guyana’s offshore. A by-product of the operation is natural gas which was initially reinjected into the reservoir or flared. In 2017, the Government commissioned a study to ascertain whether the gas could be brought ashore and converted into electricity. The study concluded that transporting 30-50 million cubic feet of gas daily is feasible.
The next stage was the selection of a suitable location as the landing site for the gas and the construction of a plant to convert the gas to electricity. Clonbrook on the East Coast of Demerara was considered the favoured site. However, with the change of Government in 2020, Wales was chosen instead. It is not clear whether the decision to change the location for the plant was based on sound economic analyses and/or reasoning; or whether political considerations took precedence, considering the closure of the Wales Sugar Estate by the previous Administration resulting in the displacement of workers. The overwhelming major of employees in the sugar industry, it is to be noted, are the staunchest supporters of the ruling party.
In 2021, the Government announced plans for a subsea pipeline from the ExxonMobil’s operations in the Liza field to the West Demerara shore, and the construction of a natural gas liquids plant and a gas-fired power plant at Wales. This involves Exxon’s laying of approximately 225 kilometers of pipeline, with the Government constructing a 300 megawatt gas-fired power plant and a natural gas processing facility.
The Government has stated that objective is reduce electricity generation costs substantially, thereby reducing electricity tariffs by about 50 percent before the end of 2025. In fact, during his inaugural address on 7 September 2025, the President had stated that electricity tariffs will be halved by virtue of the Gas-to-Energy Project coming on stream.
Commencement of the Project, costs and completion date
The Project commenced in 2022 at an estimated cost of $104 billion, with a completion date of December 2025, which date was revised to June 2026. Volume III of the 2026 Estimates now show a new planned completion date of December 2027, and a revised estimated cost is $276.823 billion. As of 31 December 2025, amounts totalling $258.196 billion, or 93.27 percent of the revised budget, was expended. The above cost, however, does not include approximately US$1 billion, equivalent to G$208.5 billion that ExxonMobil spent on the acquisition and laying of the pipeline from its offshore operations to Wales.
Considering the amount of $10.717 billion shown in the 2026 Estimates, and the two Supplementary Estimates as reflected in Financial Papers 1 & 3 of 2026 amounting to $43.787 billion, the cost of the Project is estimated to be $312.7 billion by the end of the year. Taking into account additional resources to be included in the 2027 Estimates, that cost is likely to reach $400 billion which is four times the original estimate made in 2022!
The above cost also does not include the contractor’s claim of US$102 million for additional expenditure incurred, due to delays in handing over the site for work to commence. This includes the failure to complete as per schedule the access road to the construction site, and the need to stabilize the soil at the construction site that necessitated costly additional works. The latter raises the important question as to whether any geotechnical survey was carried out to determine the suitability of the location before the site was chosen.
The above claim was referred to a Dispute Avoidance/Adjudication Board which awarded the above sum to the contractor. The status of the dispute, however, remains unclear as both sides indicated that they are not in agreement with the award. There are unconfirmed that certain payments have since been made to the contractor in relation to the dispute, but the Government has denied making any such payments.
The contractor’s claim is considered a contingent liability and should be reflected in Statement of Contingent Liabilities which is one of the statements constituting the public accounts. The Fiscal Management and Accountability Act defines a contingent liability as ‘a future commitment, usually to spend public moneys, which is dependent upon the happening of a specified event or the materialisation of a specified circumstance’. An examination of the Statement of Contingent Liabilities as of 31 December 2025, however, revealed that this amount was not included. The Statement was audited by the Auditor General who did not comment on this omission and who gave a clean opinion on said statement!
Project financing
The Gas-to-Power Project is financed through a combination of funding by ExxonMobil, the Government of Guyana and US EXIM Bank. As indicated above, Exxon is responsible for the laying of the pipeline to bring the gas to Wales. The related expenditure is considered recoverable costs to be included in the calculation of cost oil and hence a deduction from profit oil. It will spread over a 20-year period at US$55 million per annum, resulting in a reduction in Guyana’s share of profit oil by US$27.5 million.
The US EXIM Bank loan is for US$527 million, the purpose of which is to procure from US companies all the necessary equipment and other materials for the plant. The loan agreement was signed December 2024. However, as of 31 December 2025, no disbursements were made on the loan. Last September, the Government requested the Bank to approve of an extension of the deadline for the final disbursement of the loan, which approval was granted to 30 December 2027.
Additionally, in July 2023, the Government awarded a contract of US$159.9 million to an Indian company for the construction of the transmission lines and substations needed to supply electricity from the Wales plant to consumers. However, it is not clear how much was paid to the contractor as at 31 December 2025 and whether the amount is included in the overall cost of $258.916 billion as at that date which has so far been financed by the Government.
Latest development
Last Thursday, the Vice President gave an update on the Gas-to-Power Project in which he stated that the simple cycle unit is expected to be completed in four months’ time, with the combined cycle stage to around June next year. Meanwhile, it is unclear how long more consumers have to wait to receive the benefit of reduced electricity tariffs.