One contractor dismissed from A-Line pump station, second one behind schedule – Auditor General’s Report

The point at which the first contractor was dismissed.

The 2025 Auditor General’s report points out that one contractor for the pump station at A-Line Sluice, West Coast Demerara (WCD) was dismissed while the second is now behind schedule and there are questions about the recovery of monies and the enforcement of bonds.

The examination by the audit office underlines major problems that the government has had with pump stations where contracts have gone to persons who were not qualified leading to large questionable expenditures and extensive delays.

In. The case of the A-Line Sluice pump station, the first contract was signed on May 12, 2022.  More than four years and six months later, the project is still to be completed.

The first contract signed was worth $717m with a commencement date of June 1, 2022 and a completion date of 31st May, 2023.   It had been awarded to Civcon Engineering Contractors. However, because of a default by the contractor the contract was terminated on 31st May, 2024 – a year after the proposed completion date. Moreover, as at December 31, 2025, amounts totalling $156.6m had been paid to the contractor.  The Auditor General’s Report said that it found that the Advance Payment Bond had expired and only $28.1m out of $107.5m of the advance payment was recovered with a balance of $94.4m still to be retrieved by the National Drainage and Irrigation Authority (NDIA).  Similarly, the performance bond had expired and the NDIA failed to levy on the bond and recover $71.7m due to the NIDIA as a result of the contractor’s defaulting. Furthermore, the audit office said that the NDIA did not apply any liquidated damages.

The Ministry in its response to the report acknowledged the observations and said that a letter had been sent to the insurance company to levy on the bond.

In response, the audit office admonished the ministry to pursue the recovery of all outstanding amounts and “in future,  ensure that liquidated damages are applied in accordance with the conditions of the Contract”.

The contract for the pump station was then re-tendered and an award made by the National Procurement and Tender Administration Board in the sum of $390.2m against an engineer’s estimate of $432m.

The state of the pump station when visited in September this year.

At the time of reporting in September of 2026, the contractor received an advance payment of $58.5m representing 15% of the contract sum followed by four interim payments totalling $45.9m. At the time of reporting in September 2026, $12m or 21% of the advance payment had been recovered. 

The audit office said that a physical verification on September 2nd 2026 showed that works were ongoing with the installation of 64 CFA piles, heavy-duty revetment  and wall foundations on the north and south sections finished while formwork and reinforcement preparation for the pile caps and the second concrete lift on the north wall and third concrete lift on the south wall were in progress. At the time of reporting, the report said that the contractor had been granted an extension to December 31, 2026.

The ministry acknowledged the audit office’s statement and said that the re-tendered contract had been awarded to Sheriff Construction Inc. As at June 8 2026, 32% of work had been completed and all foundation piles had been driven to the required elevation. The contractor has been paid the sum of $102.8m to date.

You reached the end of this article without encountering a paywall.

That is deliberate. We believe reliable journalism about Guyana should be available to everyone from the hinterland to the coast, including those who cannot afford to pay for it. But investigating, reporting and publishing every story takes time, energy and resources. Keeping our journalism open depends on the commitment of readers who can chip in and contribute to help cover the cost for everyone.

Please join the Kiskadee family by taking a subscription. Every contribution counts to our commitment to our journalists, to our readers, and to independent, public-interest journalism.

And please spread the word. One one dutty build dam!

Become a supporter